In progress

Nakhodka Mineral Fertiliser Factory

About Project02

  • Customer

    NZMU JSC

  • Implementation timeline

    2019-2023

  • Place

    Nakhodka

  • Investments

    RUB 165 bln (the first stage of construction)

  • Roles of LLC PMCC

    Supervisory company (construction audit, financial and technical supervision)

Project Characteristics

NZMU is a large-scale investment project for the construction of a plant for the production of methanol and nitrogen fertilizer. The plant will be built near the large seaport of Nakhodka, close to the targeted market - the Asia-Pacific region. India and Latin America will also be reachable from a logistical point of view.

It is planned that the plant will produce 1.8 million tons of methanol (1st stage) and 3 million tons of carbamide (2nd stage) annually.